Site check: 4 × 150 kW chargers at 100 Example Road
The question
Can the nearby feeder take about 600 kW of new charging load (all four chargers at full power at once), and has its published capacity changed since the contractor's January quote?
The answer
Phase 1 fits under the published figure, with less room than in January. The published load-serving headroom on Example Feeder 12 fell from 2.4 MW to 0.9 MW when Example Utility refreshed its map on April 15. 600 kW still fits under the new figure; a second phase of the same size would not. If the January quote assumed phase 2, re-scope it before the client signs.
Nearby feeders
| Feeder (synthetic) | Distance | Published headroom | Change |
|---|---|---|---|
| Example Feeder 12 | 0.2 mi | 0.9 MW | Changed Apr 15 (was 2.4) |
| Example Feeder 14 | 0.6 mi | 3.1 MW | Unchanged since Feb 25 |
| Example Feeder 9 | 0.4 mi | – | Dropped off the map Apr 15 |
Distances are to the nearest line section. The utility hasn't confirmed which feeder serves the site.
What this metric means
Load-serving headroom is the utility's estimate of how much new load a feeder can take before upgrades. It is not a hosting-capacity figure for solar or storage, and it doesn't cover the transformer or service at your site.
It also doesn't show requests other customers have already made on the feeder; nobody holds the headroom for you. Other utilities publish other measures, such as EV hosting capacity or electrification headroom, and every check names the one it uses. This is a screening answer from published data, not a capacity study.
Ask the utility
Can Example Feeder 12 serve an additional 600 kW at 100 Example Road in 2027, and does the April 15 figure change the service or line-extension work you'd expect?